ChiliProject is not maintained anymore. Please be advised that there will be no more updates.

We do not recommend that you setup new ChiliProject instances and we urge all existing users to migrate their data to a maintained system, e.g. Redmine. We will provide a migration script later. In the meantime, you can use the instructions by Christian Daehn.

Scope and release plan 1.1.0 (Task #117)


Added by Eric Davis at 2011-02-01 07:11 am. Updated at 2011-02-14 11:26 pm.


Status:Closed Start date:2011-02-01
Priority:Normal Due date:2011-02-05
Assignee:Eric Davis % Done:

0%

Category:ChiliProject - Organization
Target version:1.1.0 — Bell
Remote issue URL:

Description

Need to decide what 1.1.0 should have. We should focus on staying compatible with Redmine (which version?) but start to fix some of the minor bugs that are allowed in a minor release cycle.


History

Updated by Felix Schäfer at 2011-02-01 10:49 pm

  • Status set to Open

Updated by Eric Davis at 2011-02-03 01:29 am

Since 1.1.0 will be released very soon we need to figure out what will be included in it this week. I can commit to:

What else could people commit to for 1.1.0? Ideally it would need to be done by the weekend of the 19th so we have time to release testing.

  • Due date set to 2011-02-05

Updated by Eric Davis at 2011-02-06 01:51 am

Anyone else want to work on something for 1.1.0?

Updated by Felix Schäfer at 2011-02-06 12:24 pm

To be honest I have to catch up a little on work and my studies :-) I'll see to throw in some of the low-hanging ones, but no big code hunks from me for this, sorry.

Updated by Eric Davis at 2011-02-14 11:26 pm

I'm closing out the 1.1.0 scoping. Since this is a minor release, if there are some more bug fixes that get done a few days before the release we can try to include them. I'd like to have about a week or so before the release to test out our release process.

  • Status changed from Open to Closed